Moore & WallerMotorpoint RAMS

Competent-person review required before issue. Jordan Lee Waller must confirm the site conditions, release checks, chosen access equipment and specialist-trade controls, then sign and date this RAMS before the workforce is briefed.

MW-MPW-RAMS-001 · Revision 01

Risk assessment & method statement

Wall reinstatement beneath canopy and new toilet block

Site

Motorpoint, Derby Road, Widnes, Cheshire, WA8 9WZ

Programme

7 September–mid-December 2026 · Monday–Thursday · 07:00–19:00

Principal contractor

Moore and Waller Building and Roofing Ltd

Client / designer

Motorpoint PLC · Pier Architects Ltd

Project / H&S manager

Jordan Lee Waller · 07557 471773

Project correspondence

jordan@mooreandwaller.co.uk

Site manager

Charlie Miller

Site supervisor

Rory Hull

Workforce

Up to five people per day

Document control

Purpose, limits and authority

Covered by this RAMS

  • Site set-up, public segregation, planned deliveries and material storage.
  • Non-structural wall or partition reinstatement beneath the canopy.
  • Toilet-block framing, boarding, sanitary fit-out and finishes.
  • Normal use of portable power tools, drilling and controlled cutting.

Not covered without separate approval

  • Structural demolition, load-bearing alteration or temporary works not supported by an approved design.
  • Asbestos disturbance, excavation, roof work, lifting operations or live service work.
  • Hot work, scaffold or MEWP activity without a specific assessment, inspection and permit where required.
  • Any change to the work, location, materials, workforce or site conditions not reviewed at the daily briefing.
Stop-work authority: every worker must stop and tell Charlie Miller or Jordan Lee Waller if the work differs from this document, a control is missing, the public enter the work zone, an unknown service/material is found or conditions become unsafe. Work restarts only after reassessment and briefing.

Release gate

Checks required before the RAMS is issued

Latest construction drawings and specification available
Wall/partition confirmed non-structural or engineered temporary-works design issued
Asbestos register and refurbishment/demolition survey checked for the work area
Existing services located; isolation and permit arrangements confirmed
Access equipment selected and inspection records available
Product safety data sheets and COSHH assessments available
Subcontractor RAMS reviewed for electrical, plumbing or specialist work
Public segregation, delivery route and emergency access checked on site

Risk assessment

Hazards and control measures

Likelihood

1 Rare · 2 Unlikely · 3 Possible · 4 Likely · 5 Almost certain

Severity

1 Minor · 2 Moderate · 3 Serious · 4 Major · 5 Fatal

Score

1–5 Low · 6–10 Medium · 11–15 High · 16–25 Very high

Score = likelihood × severity. Ratings are the project draft and must be validated against actual site conditions by the approving competent person. Residual ratings assume every listed control is in place.

01

Customers, visitors and public interface

At risk: Public, Motorpoint staff, workforce

Initial risk

25 · Very high

Residual risk

5 · Low

  • Maintain solid barriers, locked or controlled gates and clear warning signs between the live dealership and construction area.
  • Use the side-gate route only. Keep the showroom restricted unless the site manager expressly authorises access.
  • Stop work immediately if a member of the public enters the exclusion zone; make the area safe before work restarts.
02

Vehicle movements and deliveries

At risk: Drivers, workforce, public

Initial risk

20 · Very high

Residual risk

5 · Low

  • Book deliveries in advance and agree the route, unloading point and time with Charlie Miller.
  • Enforce 5 mph with hazard lights. Separate pedestrians and vehicles and keep emergency access clear.
  • Avoid reversing; where unavoidable, exclude pedestrians and use a trained, authorised banksman in high-visibility clothing.
03

Unexpected services, asbestos or structural instability

At risk: Workforce, occupants, public

Initial risk

20 · Very high

Residual risk

5 · Low

  • Before intrusive work, check drawings, service information, asbestos register/survey and confirm whether any wall or element is structural.
  • Competent persons must isolate, lock off and prove dead services before disturbance. Mark known services and brief the team.
  • No structural alteration, temporary works or suspected asbestos disturbance is covered. Stop, isolate the area and escalate to Jordan Lee Waller.
04

Work at height and access equipment

At risk: Workforce, people below

Initial risk

20 · Very high

Residual risk

5 · Low

  • Avoid work at height where possible. Select an inspected podium, tower, scaffold or MEWP appropriate to the task and ground conditions.
  • Only competent, authorised people may erect or operate access equipment. Use guardrails, toe boards and exclusion zones where required.
  • Ladders are for short-duration, light work only after assessment; maintain three points of contact and never overreach.
05

Falling materials and tools

At risk: Workforce, Motorpoint staff, public

Initial risk

16 · High

Residual risk

4 · Low

  • Create a controlled exclusion zone below overhead work and never work above another person.
  • Secure tools and materials; fit toe boards or suitable containment where required. Do not store loose items at edges.
  • Wear hard hats wherever overhead work creates a falling-object risk.
06

Construction dust, including silica and plasterboard dust

At risk: Workforce, Motorpoint staff, public

Initial risk

20 · Very high

Residual risk

8 · Medium

  • Eliminate or reduce cutting; use pre-cut materials where practicable and place the cutting station away from occupied areas.
  • Use water suppression or suitable on-tool extraction with an M-class vacuum. Never dry sweep or use compressed air for dust cleanup.
  • Provide task-appropriate, face-fit-tested RPE where the assessment requires it; keep segregation until dust has been removed safely.
07

Abrasive wheels, drilling and portable power tools

At risk: Operators, nearby workers

Initial risk

20 · Very high

Residual risk

5 · Low

  • Only trained, authorised operators may use abrasive wheels. Complete pre-use checks and use the correct undamaged disc, speed rating and guard.
  • Goggles are mandatory for abrasive-wheel work; add face, hearing, hand and respiratory protection where the task assessment requires it.
  • Use two hands, maintain a stable stance, keep others outside the cutting zone and isolate the tool before adjustment or disc changes.
08

Electricity and temporary supplies

At risk: Workforce, occupants

Initial risk

15 · High

Residual risk

5 · Low

  • Prefer battery or 110 V tools. Inspect tools, plugs, leads and chargers before use and remove damaged equipment from service.
  • Route leads to prevent damage and trips; use suitable RCD protection where required. Keep electrical equipment away from water.
  • Only a competent electrician may isolate, connect, test or energise fixed installations. No live working is permitted under this RAMS.
09

Manual handling of boards, blocks, sanitaryware and materials

At risk: Workforce

Initial risk

12 · High

Residual risk

6 · Medium

  • Plan deliveries close to the point of use. Check weight and route before moving any load.
  • Use trolleys, board carriers or other mechanical aids; split loads and use a coordinated team lift for large or awkward items.
  • Keep routes level, clear and well lit. Do not lift beyond individual capability and rotate repetitive handling tasks.
10

Noise and hand-arm vibration

At risk: Operators, nearby workers and occupants

Initial risk

16 · High

Residual risk

8 · Medium

  • Choose low-noise, low-vibration methods and equipment; maintain tools and use sharp, suitable accessories.
  • Plan and record trigger time, rotate work and observe exposure limits. Stop if numbness, tingling or blanching occurs.
  • Establish hearing-protection zones where required and coordinate noisy work with Motorpoint to protect staff and customers.
11

Cement, adhesives, sealants, cleaners and other substances

At risk: Workforce, occupants

Initial risk

12 · High

Residual risk

4 · Low

  • Approve products before use and retain current safety data sheets and task-specific COSHH assessments on site.
  • Use the least hazardous suitable product, provide ventilation and wear the gloves, eye protection or RPE stated by the assessment.
  • Keep products labelled and closed, store them securely and follow spill, first-aid and disposal instructions.
12

Slips, trips, sharp edges and housekeeping

At risk: Workforce, visitors

Initial risk

12 · High

Residual risk

4 · Low

  • Maintain clear pedestrian and emergency routes; manage cables and remove offcuts, packaging and spills as work proceeds.
  • Provide adequate lighting and use designated skips. Never allow waste or materials to obstruct doors, extinguishers or access routes.
  • Wear suitable gloves for sharp materials and protect or remove protruding fixings immediately.
13

Fire, hot work and emergency access

At risk: Everyone on site and in Motorpoint

Initial risk

20 · Very high

Residual risk

5 · Low

  • No hot work is covered by this RAMS. A separate hot-work assessment, permit, fire watch and suitable extinguishers are required.
  • Keep escape routes, break-glass points and extinguishers beside room doors accessible. Do not block emergency-vehicle access.
  • Check the shift fire board before work. On alarm, stop work, leave by the nearest safe exit and report at the front-car-park assembly point.
14

Weather, wind, wet surfaces and low light under the canopy

At risk: Workforce, visitors

Initial risk

12 · High

Residual risk

4 · Low

  • Inspect conditions before each shift and after weather changes. Suspend work where wind, rain, ice or poor visibility makes it unsafe.
  • Secure lightweight materials, provide suitable task lighting and keep access equipment on firm, level ground.
  • Remove standing water and contamination promptly and provide weather-appropriate PPE.
15

Distraction from mobile phones

At risk: Workforce, public

Initial risk

12 · High

Residual risk

4 · Low

  • Mobile phones may be used during designated break times in the welfare or break area.
  • For an emergency call, stop the task, isolate or place equipment safely and move to a safe location before using the phone.
  • No phone use while walking vehicle routes, operating equipment, working at height or carrying out a safety-critical task. Photography and social-media posting remain prohibited.

Method statement

Safe sequence of work

01

Pre-start review

Jordan Lee Waller and Charlie Miller review the construction-phase plan, latest drawings/specification, structural information, asbestos information, service drawings, COSHH assessments and subcontractor RAMS. Confirm permits, access equipment and any temporary works before authorising the task.

02

Daily control

All personnel enter by the side gates, sign in at the site office, complete the site induction and attend the daily briefing. Check the named fire marshal, work area, weather, barriers, lighting, emergency routes and changing interfaces. No lone working.

03

Segregate and prepare

Close and secure the work zone from Motorpoint staff and the public. Protect retained surfaces, establish pedestrian and delivery routes, position signs and barriers, and maintain emergency access. Stop if the segregation cannot be maintained.

04

Services and existing fabric

Confirm the intended work is non-structural. Locate services and arrange isolation, lock-off and proof of dead by a competent person. Do not disturb unknown materials. Any suspected asbestos, unexpected service or unstable element triggers an immediate stop-work and escalation.

05

Deliver and store

Pre-book deliveries. A trained banksman controls unavoidable reversing and unloading. Store boards, blocks, sanitaryware and fixings securely inside the compound, protected from weather, without overloading surfaces or obstructing access.

06

Set out and construct

Set out from approved drawings. Reinstate the wall or partition in controlled stages using the specified system and manufacturer instructions. Maintain stability at every stage; install tracks, studs, blocks, boards, bracing and fixings to the approved design. Do not leave an incomplete wall unsafe or unsupported.

07

Cut, drill and fix

Use a designated cutting area and the least dusty method. Fit guards and extraction or water suppression before starting. Only trained operators use abrasive wheels; goggles are mandatory. Control noise, vibration, sparks, dust and access to the zone.

08

Toilet-block fit-out

Coordinate framing, boarding, plumbing, electrical work, sanitaryware, sealants and finishes so trades do not create risks for one another. Plumbing and electrical connections, testing and commissioning are undertaken only by competent contractors under their own task controls and confirmed isolations.

09

Inspect and hand over

Remove waste as work progresses, clean with dust-safe methods and make incomplete work secure at every break and shift end. Charlie Miller completes quality and safety checks; defects, changed conditions or incomplete controls are corrected before handover or reopening the area.

Site rules

People, PPE and emergency arrangements

Minimum and task PPE

  • Safety boots and yellow high-visibility vest.
  • Hard hat where overhead work creates a falling-object risk.
  • Suitable gloves and task-specific eye/hearing protection.
  • Goggles for abrasive wheels; RPE only as specified, face-fit tested and supported by clean-shaven policy where tight fitting.

Work controls

  • No lone working. Follow approved permits and manufacturer instructions.
  • Phones only during designated breaks in the welfare or break area; emergency calls only after stopping and moving safe.
  • No radios, earphones or headphones. No photography or social-media posting.
  • Zero tolerance for alcohol, non-prescribed drugs or working while impaired.

Emergency

  • Raise the fire alarm at the nearest break-glass point and leave by the nearest safe exit.
  • Assemble in the front car park and report to the fire marshal named on the current shift fire board.
  • First-aid point: site office. Named first aiders: Charlie Miller, Jordan Waller and Lee Moore.
  • For serious emergencies call 999 and give the full Motorpoint Widnes address. Keep emergency access clear at all times.

Approval

Issue and workforce briefing record

Prepared / reviewed by

Name
Role
Signature
Date

Approved for issue by

Jordan Lee Waller
Project / H&S manager
Signature
Date
Print nameEmployer / tradeSignatureDateBriefed by
 
 
 
 
 
 
 
 

This RAMS must be briefed before work begins and reviewed after any incident, near miss, design or method change, new substance/equipment, material change in conditions, or evidence that a control is ineffective.